CICON had established fabrication unit right from its inception. Acknowledging the advantages and benefits which can be offered to clients by complementing Civil works with Pre Engineered buildings, CICON set up a full-fledged state-of-the-art fabrication factory in a 5 acre plot on NH-209 at Harohalli about 45 kilometres from Bangalore.
The main shop floor of 7500 Square metres deploys latest & sophisticated fabrication machinery capable of delivering an output of 800 Metric tonnes per month to cater to all types of fabrication works such as Pre Engineered Building, conventional fabricated structure, form work, railings, grills, gates and other specialized works. Design, fabrication and erection works are handled by a team of experienced professionals and experts in this field.
FACTORY INFRASTRUCTURE
Consists of CNC plasma cutting machine, Automated H-Beam production line, Automated shotblasting machine, Dedicated paint booth and other latest fabrication machines.
OUR PROJECTS
Fabrication & Erection of Factory Building for HUBNER INTERFACE SYSTEMS INDIA PRIVATE LIMITED at Malonagathihalli, T Begur, Nelamangala, Bangalore
Turnkey project executed to perfection and satisfaction of German client. PEB was design & build including customized vertical storage system.
Client : M/s. Hubner Interface Systems India Pvt Ltd
Architect : M/s NU Associates
Consultants : M/s Uttaram Inconstruct Llp
Fabrication Value : Rs. 1,354 Lakhs
Time : 10 Months
Area : 9,250 Sqm
Completion : September 2024
Fabrication Qty : 780 MT
Commercial Building “Brigade WTC” forBrigade Enterprises Ltd. at Rajajinagar Bangalore
This composite 10 storied steel building in triangular shape has circular CFST columns and deck sheet slabs. As the elements were pre fabricated at our factory we could achieve 15 days slab cycle.
Client : M/s. Brigade Enterprises Ltd.
Architect : M/s. Zachariah Consultants
Fabrication Value : Rs. 900 Lakhs
Time : 7 Months
Area : 9000Sqm
Completion : December 2021
Fabrication Qty : 750 MT
Fabrication & Erection of Welcome & Dining Pavilions and Car Parking for M/S Bosch Limited. At Adugodi, Bangalore
These buildings are in parabolic shape consisting of CFST columns and steel beams connected at complex junctions of varying slopes. The challenge was also to install the corrugated deck sheets in varying slopes & shapes.
Client : M/S Bosch Limited.
Consultants : M/s Knight Frank (India) Pvt. Ltd.
Fabrication Value : Rs. 560 Lakhs
Time : 7 Months
Area : 1120 Sqm
Completion : October 2023
Fabrication Qty : 550MT
Fabrication & erection of Servo & Bungee Sled work forM/s. AUTOLIV INDIA PVT LTD. At IT Park Area of Hi–Tech, Defence And Aerospace Park, Bengaluru.
This is a small fabrication work but worthy of mention due to complexity & accuracy requirements. We achieved required accuracy in microns.
Client :M/s. Autoliv India Pvt Ltd
Architect : M/s.Venkataramanan Associates
Consultants : M/s.Facilities & Building Solutions Pvt Ltd
Fabrication Value : Rs. 42.64 Lakhs
Time : 2 Months
Completion : December 2020
Fabrication Qty : 30 MT
Fabrication & Erection of Clubhouse Structure for M/s VAISHNAVI GROUP At Anjanapura Bangalore
Each built up girders weighing about 20.0 MT were erected using special crane of 500 ton capacity.
Client : M/s VAISHNAVI INFRASTRUCTURE PVT. LTD.,
Architect : M/s PTN ARCHITECTS
Consultants : M/s S & S ASSOCIATES
Fabrication Value : Rs. 200Lakhs
Time : 3 Months
Area : 1200 Sqm
Completion : Sept. 2019
BOSCH NHP 700 atTRAINING CENTRE AND CANTEEN Naganathpura, Bengaluru
Client : M/s. Bosch Automotive Electronics India Pvt Ltd
Architect : M/s. Gayathri & Namith Architects
Consultants : M/S. INNOTECH
Fabrication Value : Rs. 350.00 Lakhs
Time : 3 Months
Area : 2000 Sqm
Completion : Jan 2017
Fabrication Qty : 220MT
Industrial facility forM/s SJS ENTERPRISES PVT LTD, at Basappana Playa Cross Kengeri Hobli, Bengaluru.
PEB Structure for Canteen Building above
second floor of RCC building.
Client : M/S SJS Enterprises Pvt Ltd,
Architect : M/s. Jayam Consultants Pvt Ltd.,
Fabrication Value : Rs. 141.00 Lakhs
Time : 2.5 Months
Area : 4000 Sqm
Completion : Oct 2017
Fabrication Qty : 80 MT
Institutional Project for PRESIDENCY GROUP OF INSTITUTIONS at Dibbur, Bengaluru Rural
Client : M/s Presidency Group of Institution
Fabrication Value : Rs. 390.00 Lakhs
Architect : M/s Architecture Paradigm
Time : 4 Months
Area : 2600 Sqm
Completion : May 2016
Fabrication Qty : 220MT
CMR ACADEMIC ANDADMINISTARTIVE BLOCK at Chagalatti Village Yelahanka Taluk Bengaluru.
Client : M/s. CMR University,
Architect : M/s. Shuonya Nava Designs Pvt. Ltd.
Fabrication Value : Rs. 498.00 Lakhs
Time : 4.5 Months
Area : 5000 Sqm
Completion : Dec 2015
Fabrication Qty : 410 MT
Industrial facility – Expansion Phase IV B forTOYOTA INDUSTRIES ENGINE INDIA PVT. LTD. (TIEI) at Jigani, Anekal Taluk, Bengaluru.
Client : M/S. TOYOTA INDUSTRIES ENGINE
INDIA PVT. LTD.
Architect : M/s STUP CONSULTANTS PVT. LTD
Fabrication Value : Rs. 300 Million
Time : 7 Months
Area : 25,500 Sqm
Completion : 2014
Fabrication Qty : 2500 MT
Industrial facility unit for BOSCH REXROTH (INDIA) LIMITED at Sanand, Ahmedabad
M.S Tubular Truss & Lattice grid structure with
span of 18M x 12M The roof is with double skin
kliplok galvalume sheeting with rockwool
insulation sandwiched in between.
Client : M/s Bosch Rexroth (India) Ltd,
Architect : M/s Venkataramanan Associates
Fabrication Value : Rs. 2500 Lakhs
Time : 7 Months
Area : 25,500 Sqm
Completion : Dec 2012
Fabrication Qty : 2,300 MT
Factory Building forPIERBURG INDIA PVT. LTD., at Takawe, Pune.
Client :M/s Pierburg India Pvt. Ltd.
Fabrication Value : Rs. 800.00 Lakhs
Consultants : M/s Indo-Genman Project Consultancy,
Time : 5 Months
Area : 9000 Sqm
Completion : Dec 2008
Fabrication Qty : 500 MT
Expansion of Factory Building forDENSO KIRLOSKAR INDUSTRIES PRIVATE LIMITED at Nelamangala, Bengaluru
Client : M/s Denso Kirloskar Industries Pvt. Ltd.,
Architect : M/s Stup Consultants Pvt. Ltd
Fabrication Value : Rs. 900 Lakhs
Time : 5 Months
Area : 11,500 Sqm
Completion : Nov 2009
Fabrication Qty : 850 MT
INNOVATION HUB SSS REALTY & CO. at Koramangala, Bengaluru.
Supply of conventional built-up Plunge columns.
Client : M/s SSS Realty & Co,
Consultants : M/s Innotech Engineering Consult Pvt.Ltd,
PMC : M/s Colliers International Group Inc,
Fabrication Value : Rs. 225.00Lakhs
Time : 40 Days
Completion : June 2024
Fabrication Qty : 190 MT
Bus Body facility forVOLVO BUS BODY TECHNOLOGIES INDIA PVT. LTD., at Hoskote, Bengaluru.
Client : M/s Volvo Bus body Technologies India Pvt. Ltd.,
Consultants & PMC : M/s Wilbur Smith Associates Pvt. Ltd.
Fabrication Value : Rs. 650.00Lakhs
Time : 5 Months
Area : 14500 Sqm
Completion : Jan 2009
Fabrication Qty : 600 MT